Committee Meeting 3
July 27, 2021
Planning a climate-ready future for 2 multi-use piers, nearly 7 acres of park, and more than 1,000 feet of shoreline in the heart of Rockland.
Progress to Date
Implementation Funding
March 2024
$4,060,000 for Middle Pier and Buoy Park included in a Congressional Appropriations Bill signed by the President
October 2023
Congressionally Directed Spending Request included in relevant Senate Appropriations Bill.
September 2023
Maine Department of Transportation includes $250,000 to assist with Middle Pier redevelopment in its Fiscal Year 2025 Work Plan.
March 2023
Request for $4,060,000 in Congressionally directed spending to assist with Phase 1 implementation - Middle Pier and Buoy Park.
Honors
May 2024
Maine Association of Planners Project of the Year Award
January 2024
Governor Mills mentions the importance of this project in her State of the State address
April 2022
Earth Day site visit from Governor’s Office of Policy, Innovation & The Future (GOPIF)
Permitting
Winter 2023-24
Permitting for the marine infrastructure underway.
Preliminary Engineering Phase – Landside Improvements
October 2023
Preliminary design report completed. Review or download the Preliminary Design Report here.
Preliminary design plans for the upland completed. Review or download preliminary design plans here.
April 2023
Preliminary design for the landside improvements kicks off.
March 2023
Pre-design work (survey updates, geotechnical investigation) for landside begins.
January 2023
Community Action Grant Award for preliminary engineering of landside improvements
Preliminary Engineering Phase – Marine Infrastructure
March 2023
Preliminary design report for the marine infrastructure finalized. - Review or download here
February 2023
Preliminary Design for the Marine Infrastructure portion of the Downtown Waterfront Plan completed - Review or download here
October 2022
Marine Infrastructure Assessment completed - Review or download here
September 2022
Revised project website launched – www.rocklanddw.info
September 2022
Community Action Grant application for preliminary engineering of landside Marine infrastructure submitted.
September/October 2022
Pre-design work for marine infrastructure underway (additional survey work and more detailed facility assessment)
Summer 2022
Contract established with consulting team led by Landmark Corporation preliminary engineering of the marine infrastructure
Spring 2022
Community Action Grant Award of $50,000, for preliminary engineering of marine infrastructure
Conceptual Design Phase – Complete
June 2022
Implementation Road Map for the Conceptual Design complete – Review or download here
Spring/Summer 2022
Ad Hoc Downtown Waterfront Committee, Harbor Management Commission, Parks & Recreation Advisory Committee, Harbor Trail Committee, participating stakeholder, and City Council review and endorsements of Conceptual Design
Spring 2022
Climate-ready Conceptual Design completed – Review or download here
2021-Spring 2022
Collaborative Committee and stakeholder meetings, site tour and workshops that established shared goals and objectives and guided development of the Conceptual Design and the Road Map for its implementation
Summer 2021
Community Survey – Results summarized in the Conceptual Plan and Road Map - Review or download here
Spring 2021
Project website established - www.rocklanddw.info
Spring 2021
Contract with Consulting team led by the Musson Group
Fall 2020
Shore & Harbor Planning Grant award of $30,000 from the Maine Coastal Program for consulting support