Committee Meeting 3
July 27, 2021

Planning a storm-resilient future for the 2 multi-use piers, nearly 7 acres of park, and more than 1,000 feet of shoreline in the heart of Rockland. This vision, developed in collaboration with a project advisory committee and community input, includes multiple projects that can be implemented.
Progress to Date
Implementation Funding
February-April 2026
Applications for federal funding to assist with redevelopment of the Public Landing and Harbor Park
​
March 2026
Application to the Maine Public Working Waterfront Grant Program for supplemental funding for Middle Pier
March 2024
$4,060,000 for Middle Pier and Buoy Park included in a Congressional Appropriations Bill signed by the President
October 2023
Congressionally Directed Spending Request included in relevant Senate Appropriations Bill.
​
September 2023
Maine Department of Transportation includes $250,000 to assist with Middle Pier redevelopment in its Fiscal Year 2025 Work Plan.
​
March 2023
Request for $4,060,000 in Congressionally directed spending to assist with redevelopment of Middle Pier & Buoy Park.
Honors
May 2024
Maine Association of Planners Project of the Year Award
January 2024
Governor Mills mentions the importance of this project in her State of the State address
​
April 2022
Earth Day site visit from Governor’s Office of Policy, Innovation & The Future (GOPIF)
Permitting
December 2025
Middle Pier & Buoy Park permitting complete, including US Army Corps, Maine DEP NRPA, and Maine DEP Stormwater Permit by Rule
December 2025
Public Landing & Harbor Park partially complete; Maine DEP NRPA permit obtained, US Army Corps permit underway
​
Preliminary Engineering Phase – Landside Improvements
October 2023
Preliminary design report completed. Review or download the Preliminary Design Report here.
Preliminary design plans for the upland completed. Review or download preliminary design plans here.
April 2023
Preliminary design for the landside improvements kicks off.
​
March 2023
Pre-design work (survey updates, geotechnical investigation) for landside begins.
​
January 2023
Community Action Grant Award for preliminary engineering of landside improvements
Preliminary Engineering Phase – Marine Infrastructure
March 2023
Preliminary design report for the marine infrastructure finalized. - Review or download here
​
February 2023
Preliminary Design for the Marine Infrastructure portion of the Downtown Waterfront Plan completed - Review or download here
​
October 2022
Marine Infrastructure Assessment completed - Review or download here
September 2022
Revised project website launched – www.rocklanddw.info
September 2022
Community Action Grant application for preliminary engineering of landside Marine infrastructure submitted.
​
September/October 2022
Pre-design work for marine infrastructure underway (additional survey work and more detailed facility assessment)
​
Summer 2022
Contract established with consulting team led by Landmark Corporation preliminary engineering of the marine infrastructure
​
Spring 2022
Community Action Grant Award of $50,000, for preliminary engineering of marine infrastructure
​
Conceptual Design Phase – Complete
January 2026
Final design for Middle Pier & Buoy Park complete
March 2023
Preliminary design report for marine infrastructure complete
February 2023
Preliminary design report for upland infrastructure complete